+The following M3 original plan deliverables did
+not make it into this build:
+
+- The Wizard is not yet completely replacable.
+- User Actions, and Import/Export were deferred.
+ A new plan will be published.
+- JUnit tests are not yet available.
+
+The following critical or major bugs are currently known. Since
+the goal of this milestone was "functional complete" for soliciting
+user and API feedback, we still gave a go for this milestone.
+We'll strive to fix these as soon as possible.
+
+ - bug 143462 - maj - [updating] Dirty remote editors do not get notified
+ - bug 143292 - maj - [mac] Move Resource dialog causes hang/crash
+ - bug 142712 - maj - [team] Connection created in Team profile is not functional
+ - bug 142710 - maj - [team] NPE when trying to copy or move a connection to a team profile
+ - bug 139207 - maj - Browsing into some remote tar archives fails, and may crash the dstore server
+
+Click
+here
+for an up-to-date list of major or critical bugs, or
+here
+for a complete up-to-date bugzilla status report, or
+here
+for a report on bugs fixed so far.
+
+ |